Case Study

Grade-A Office Tower: Cat6A Structured Cabling & Fiber Backbone Supporting 1,500 Users

15-year structured-cabling warranty issued; first-fit cabling completed 2 weeks ahead of schedule.

  • Client

    New-build Grade-A office tower

  • Location

    Gulshan, Dhaka

  • Delivered

    2025

  • Project Status

    2025

Client Organization

New-build Grade-A office tower

Deployment Location

Gulshan, Dhaka

Completion Year

2025

Brands & Systems

Tier-1 Certified

The challenge

Client Profile

A new 22-floor Grade-A commercial office tower completed in early 2026 in Bashundhara City, Dhaka — one of Bangladesh's most rapidly developing commercial real estate zones. The building was developed by a major Bangladeshi real estate company and leased to five corporate tenants prior to completion: a multinational pharmaceutical company (6 floors), a national insurance company (5 floors), a local private bank (4 floors), a technology services firm (4 floors), and a logistics company (3 floors). The developer was responsible for delivering the building's base-build infrastructure — including structured cabling — to a Grade-A specification that would satisfy all five tenants' technical requirements and allow their respective fit-out works to proceed on a shared completion date.

The challenge

The Challenge

The developer had committed to delivering the base-build infrastructure by a fixed date to align with all five tenants' lease commencement dates, which were contractually linked to the building handover. Any delay in base-build completion would cascade into tenant fit-out delays and potentially trigger lease commencement penalties. The structured cabling scope — 22 floors, 1,500 data ports, fiber backbone, and MDFs — was on the critical path: tenant IT teams could not begin fit-out network installation until the base-build structured cabling was certified and handed over.

The five-tenant configuration presented a specific technical challenge: all five tenants required their own logically and physically separate network infrastructure, but they would share the building's vertical fiber backbone risers and the two Main Distribution Frames (MDFs) in the building's basement plant rooms. The structured cabling design needed to support:

  • Five separate tenant networks on the same horizontal cabling infrastructure, with physical and logical separation maintained throughout
  • A shared-backbone fiber infrastructure that carried all five tenants' vertical traffic in a managed, non-conflicting arrangement
  • Sufficient port density and fiber capacity to support each tenant's projected 5-year growth without requiring additional cabling
  • 10GbE capability at every data port — a Grade-A specification requirement that mandated Cat6A (not Cat6) as the minimum horizontal cabling standard

The developer's project manager had received a proposal from a local cabling contractor that specified Cat6 (not Cat6A) cabling on cost grounds, presenting it as equivalent for current use. The developer's IT consultant had rejected this, noting that Cat6 is not tested for 10GbE at distances beyond 55 metres — insufficient for a 22-floor building where horizontal cable runs can reach 90 metres from MDF to remote ports. Cat6A, tested to 100 metres for 10GbE, was the correct specification for the building's dimensions. This early technical debate had sensitized the developer's project team to the importance of specifying and verifying the correct cabling standard.

The developer also required that the completed infrastructure be independently certified to TIA-568-C.2 — with test results for every cable link submitted as part of the handover documentation package. This certification requirement protected the developer's warranty position and gave the five tenant IT teams an independently verified baseline for their network infrastructure.

Why SSAL

Why SSAL

SSAL was selected through a competitive procurement process managed by the developer's project manager. Three structured cabling contractors submitted proposals. SSAL was selected based on the Commscope SYSTIMAX brand specification — Commscope's SYSTIMAX portfolio is one of the few cabling systems with an independently verified and documented 25-year extended warranty for systems installed by authorised installers to specification. For a Grade-A building where tenants expected long-term infrastructure reliability, the 25-year warranty was a meaningful differentiator.

SSAL's proposal also included a detailed floor-by-floor cable routing plan showing how the five tenants' horizontal cabling would be physically managed in shared riser spaces and how the fiber backbone would be colour-coded and labelled to maintain identity separation. The other vendors had not addressed the multi-tenant routing in their proposals, leaving the question of riser congestion management unanswered.

SSAL's status as a Commscope authorised installer meant that the project would qualify for the Commscope SYSTIMAX 25-year Application Assurance — a commercially important protection for the developer's warranty position.

The solution

The SSAL Solution

SSAL designed and installed a complete structured cabling infrastructure for the 22-floor building, from MDFs in the basement to 1,500 data ports on the office floors.

Horizontal Cabling — 1,500 Cat6A Ports: 1,500 data ports were installed across the 22 office floors using Commscope SYSTIMAX GigaSPEED X10D Cat6A U/UTP cable. Cat6A provides alien crosstalk (ANEXT) performance that supports 10GBASE-T at 100 metres — the full length of any horizontal cable run in this building. Each floor received an allocation of data ports based on the tenant's footprint and density specification:

  • Pharmaceutical company floors: 85 ports per floor (6 floors = 510 ports)
  • Insurance company floors: 70 ports per floor (5 floors = 350 ports)
  • Bank floors: 80 ports per floor (4 floors = 320 ports)
  • Technology firm floors: 90 ports per floor (4 floors = 360 ports)
  • Logistics company floors: 50 ports per floor (3 floors = 150 ports)

All ports terminate on Commscope SYSTIMAX 360 24-port modular patch panels in the floor-level telecommunications rooms (TRs). Each TR is a dedicated locked room per floor, with individual TR spaces allocated to each tenant on their respective floors. The TRs are linked to the floor-level fiber distribution via LC-LC fiber patch cords.

Vertical Fiber Backbone — OM4 Multimode: A 6-core OM4 multimode fiber vertical backbone was installed from each floor's TR to the primary MDF in the basement via the building's main service riser. OM4 multimode fiber supports 40GbE at 150 metres and 100GbE at 100 metres — providing headroom well beyond the current 10GbE requirement for future backbone upgrades. Six cores per floor (4 active + 2 dark spare) were specified to accommodate each tenant's current active connectivity plus spare capacity for redundant paths.

The five tenants' fiber cores are colour-coded, labelled, and managed in separate bundles within the riser, maintaining physical identity separation throughout the vertical run. At the MDFs, each tenant's fiber terminates on dedicated 24-port high-density LC fiber patch panels.

Main Distribution Frames — Primary and Secondary: Two MDFs were installed in the basement — a primary MDF in Plant Room A and a secondary/redundant MDF in Plant Room B, separated by a minimum 15 metres for geographic resilience. The primary MDF houses the building's main backbone termination for all five tenants, with each tenant's infrastructure physically separated in dedicated rack sections. The secondary MDF provides a redundant termination point for tenants requiring MDF-level redundancy (the bank's floors were specifically specified with dual-MDF fiber diversity). Both MDFs are housed in 42U racks with cable management, hot-and-cold aisle cooling provision, and managed power distribution.

Physical Layer Documentation and Labelling: Every cable in the installation — all 1,500 horizontal runs and all 132 fiber cores in the vertical backbone — was labelled at both termination points with a unique identifier following the ANSI/TIA-606-B labelling standard. Complete as-built documentation — floor plans showing cable routes, link record for every port, patch panel schedule, fiber termination schedule — was delivered in both printed and CAD/digital format as part of the handover package.

TIA-568-C.2 Certification Testing: All 1,500 horizontal cable links were tested using a Fluke DSX-8000 cable analyser at the Cat6A specification (all test parameters including insertion loss, NEXT, ANEXT, return loss, and propagation delay), with pass/fail results for each link compiled into the Fluke LinkWare reporting format. 1,488 links passed on first test; 12 links required remediation (8 had connector termination faults, 4 had cable damage from civil works after cabling was installed — which the civil contractor repaired under their scope). All 1,500 links achieved a pass result before handover.

Implementation

Implementation

The project was delivered in 16 weeks, running concurrently with other building fit-out trades (electrical, HVAC, civil finishes). Structured cabling on a multi-tenant building under active construction requires close coordination with the main contractor's programme: cabling must be installed after ceiling void access is available (post-HVAC duct installation) but before ceiling boarding closes the void permanently.

SSAL deployed 24 installation technicians across the 22 floors, organized by floor teams to maintain pace with the construction programme. Cable pulling on each floor was sequenced to follow HVAC duct installation by 5 working days — the minimum interval the construction programme allowed. Termination and patch panel installation followed cable pulling by approximately 10 days per floor.

The riser installation — fiber backbone and inter-floor cable management — was completed as a dedicated 3-day task per riser zone, coordinated with the electrical contractor who was running power cable in the same riser space.

"We had five tenants all moving in at once, each with their own IT team and their own requirements. The cabling had to work for all of them, and it had to be certified to a standard they could all independently verify. SSAL delivered the TIA certification for 1,500 ports, the as-built documentation, and the handover on the date we needed. Not one of our five tenants raised a cabling issue during their fit-out. For a developer with that much lease commitment riding on a single handover date, that outcome is the definition of success."

Project DirectorCommercial Real Estate Developer, Dhaka
Outcome

Results & Impact

TIA-568-C.2 certification was achieved across all 1,500 data ports, with the complete Fluke test report submitted to the developer's project manager as part of the handover package. The certification confirmed 10GbE-capable infrastructure throughout the building at all horizontal run lengths.

All five tenants commenced their IT fit-out works on the scheduled handover date. None of the five tenants raised any cabling-related snags during their fit-out works — a result the developer's project manager specifically noted in the project close-out review as unusual for a large-scale structured cabling installation.

The Commscope SYSTIMAX 25-year Application Assurance warranty was registered for all 1,500 ports and the fiber backbone, providing the developer and all five tenants with long-term infrastructure assurance. The bank tenant's IT team specifically acknowledged the dual-MDF fiber diversity in their technical sign-off.